Project: Bündel Emmendingen – Lahr

Route (4000) Mannheim Hbf – Basel – Konstanz (DB-Border)

Project – an overview:
Construction phase 10: GE and PLV Emmendingen – Herbolzheim: km 177.650 – km 179.607
Construction phase 20: PLV Emmendingen – Riegel: km 187.000 – km 188.300 and km 188.680 – km 188.850
Construction phase 30: PLV Riegel – Kenzingen: km 182.100 – km 182.500
Construction phase 40: PLV Lahr – Orschweier: km 167.500 – km 168.200
Overall conversion length: 4.527m

Builder-owner:
DB Netz AG, branch southwest, I.NP-SW-M-O, 76137 Karlsruhe

Construction period: 22.07.2017 – 18.09.2017
Shift progress rate PM 1000 URM: 320 m (8 h)
Existing type of permanent way: W 60-1667-B70