Rosenheim – Ostermünchen Project from km 64.080 to km 52.180

Builder-owner: Deutsche Bahn AG, southern branch, Rosenheim network region
Construction periods:
9 May 2008 – 26 May 2008
1 August 2008 – 9 August 2008
25 August 2008 – 17 September 2008
Shift capacity PM 200-2R: 529 m
Daily capacity PM 200-2R: 1029 m

Overall conversion length: 11,900 m
Existing type of permanent way K60-1667-HH

Supplementary information further to track permanent way:
Radius: minimum radius = 531 m
Superelevation: u = 150 mm

The complete data are available for downloading as a PDF.